abusesaffiliationarrow-downarrow-leftarrow-rightarrow-upattack-typeburgerchevron-downchevron-leftchevron-rightchevron-upClock iconclosedeletedevelopment-povertydiscriminationdollardownloademailenvironmentexternal-linkfacebookfiltergenderglobegroupshealthC4067174-3DD9-4B9E-AD64-284FDAAE6338@1xinformation-outlineinformationinstagraminvestment-trade-globalisationissueslabourlanguagesShapeCombined Shapeline, chart, up, arrow, graphLinkedInlocationmap-pinminusnewsorganisationotheroverviewpluspreviewArtboard 185profilerefreshIconnewssearchsecurityPathStock downStock steadyStock uptagticktooltiptwitteruniversalityweb
Article

9 Jun 2022

Author:
Tom Azzopardi, WindPower Monthly

Mexico: EDF's Gunaa Sicarú wind energy project has contract cancelled following a court ruling

'Mexico cancels contract with controversial EDF wind farm' 7 june 2022

Mexico’s state power utility Comisión Federal de Electricidad (CFE) has cancelled the power supply contract signed with EDF Renewables for its 252MW Gunaa Sicarú wind energy project.

The cancellation was the result of a court ruling, CFE confirmed. It also follows protests by economic, social and cultural rights group ProDESC and the Union Hidalgo indigenous group who have been campaigning against the €310 million project located in the south-western state of Oaxaca...

The campaigners have opposed the project since EDF unveiled its plans in 2017, accusing the French company of signing secret agreements designed to divide the local community and contrary to the consultation process which authorities had to carry out on the project. “This cancellation serves as a precedent for the multinationals and the indigenous communities and shows that we can cancel these projects if we organise,” said Guadalupe Ramirez, a human rights campaigner from Union Hidalgo.

A spokeswoman for EDF would not comment on the decision...

The move comes as President Andres Manuel Lopez Obrador seeks to strengthen the control of CFE over the power market by limiting the market share of private power generators which have invested heavily in wind capacity over the last decade...

"This cancellation serves as a precedent for the multinationals and the indigenous communities and shows that we can cancel these projects if we organise"
Guadalupe Ramirez, a human rights campaigner from Union Hidalgo

Timeline