abusesaffiliationarrow-downarrow-leftarrow-rightarrow-upattack-typeburgerchevron-downchevron-leftchevron-rightchevron-upClock iconclosedeletedevelopment-povertydiscriminationdollardownloademailenvironmentexternal-linkfacebookfiltergenderglobegroupshealthC4067174-3DD9-4B9E-AD64-284FDAAE6338@1xinformation-outlineinformationinstagraminvestment-trade-globalisationissueslabourlanguagesShapeCombined Shapeline, chart, up, arrow, graphLinkedInlocationmap-pinminusnewsorganisationotheroverviewpluspreviewArtboard 185profilerefreshIconnewssearchsecurityPathStock downStock steadyStock uptagticktooltiptwitteruniversalityweb
Article

4 Feb 2019

Author:
Mining Review Africa (So. Africa)

Tanzania: Walkabout Resources says resettlement action plan to pave way for graphite project approved by 'local stakeholders'

"Resettlement Action Plan in Tanzania approved"

ASX-listed Walkabout Resources reports that the valuation for the Resettlement Action Plan compensation activities that were completed in 2018 has been approved by all the stakeholders and officially signed off by the Chief Government Valuator in Dodoma, Tanzania. The approval and settlement of the RAP is a major milestone which now allows on-site work to commence at the Lindi Jumbo Graphite Project in Tanzania. Executive Director of Walkabout Resources, Allan Mulligan comments:

“The milestones are being ticked off one by one. Our construction arrangements at Lindi Jumbo in Tanzania are progressing well and we are very pleased with this achievement managed by our small project team.” “The organised and well communicated execution of the RAP compensation is very important to our local communities. It validates in hard currency, the goodwill and social outcomes we have worked closely on achieving with our local stakeholders."...

This completes a lengthy and comprehensive process of public consultations, stakeholder engagement meetings, extensive fieldwork to compile all the necessary data of a process that included local communities, various government officials and external consultants. Each individual land use compensation Agreement is valid for 6 months where-after, if the company has not settled with the beneficiary, the valuation process must be repeated