abusesaffiliationarrow-downarrow-leftarrow-rightarrow-upattack-typeblueskyburgerchevron-downchevron-leftchevron-rightchevron-upClock iconclosedeletedevelopment-povertydiscriminationdollardownloademailenvironmentexternal-linkfacebookfilterflaggenderglobeglobegroupshealthC4067174-3DD9-4B9E-AD64-284FDAAE6338@1xinformation-outlineinformationinstagraminvestment-trade-globalisationissueslabourlanguagesShapeCombined Shapeline, chart, up, arrow, graphLinkedInlocationmap-pinminusnewsorganisationotheroverviewpluspreviewArtboard 185profilerefreshIconnewssearchsecurityPathStock downStock steadyStock uptagticktooltiptriangletwitteruniversalitywebwhatsappxIcons / Social / YouTube

このページは 日本語 では利用できません。English で表示されています

コンテンツは以下の言語で利用可能です: English, 简体中文, 繁體中文

ストーリー

Nepal: Civil society report alleges that Indigenous Peoples rights were denied in hydropower project development

The new report "Hanging by A Thread: Indigenous Peoples Rights in Renewable Energy Transition" exposes how Development Banks and the Nepalese government have systematically failed to protect Indigenous Peoples' rights in four major hydropower projects: Likhu, Tanahu, Upper Trishuli-1, and Upper Arun.

Despite being funded by development banks that require Free, Prior, and Informed Consent (FPIC), the report finds that FPIC processes were either entirely bypassed or reduced to performative consultations.

Communities have reported facing retaliation for demanding their rights, including detention, false charges, and militarization of their lands.

The report calls for development banks to ensure meaningful Indigenous participation and for Nepal's government to officially recognize Indigenous land rights before implementing infrastructure projects.

The Business & Human Rights Resource Centre contacted all the entities named in the report including Nepal Electricity Authority (NEA), Nepal SBI Bank, IDBI Bank, MV DUGAR, Tanahu Hydropower Limited, Manitoba Hydro International, Song Da Corporation JSC, Kalika Constructions, Power China, Lahmeyer International, Doosan Heavy Industries & Construction Ltd, Andritz, International Hydro Association, Nepal Water and Energy Development Co. Ltd., Upper Arun Hydro Electric Ltd, and SJVN. Ltd. We received a response from SBI, Lahmeyer International, Andritz, International Hydropower Association and Upper Arun Hydro Electric Ltd. We did not receive a response from the others. The responses are linked.

企業への回答リクエスト

Manitoba Hydro

回答無し

Song Da Corporation JSC

回答無し

Lahmeyer 回答を見る
Doosan Heavy Industries & Construction (part of Doosan Group)

回答無し

Andritz 回答を見る
International Hydropower Association 回答を見る
Nepal Water and Energy Development Company Pvt. Ltd. 回答を見る
Nepal Electricity Authority (NEA)

回答無し

Nepal SBI 回答を見る
IDBI Bank

回答無し

MV Dugar Group

回答無し

Tanahu Hydropower Limited

回答無し

Kalika Construction Pvt. Ltd. (Kalika Power Company)

回答無し

PowerChina (Power Construction Corporation of China)

回答無し

Upper Arun Hydroelectric Project 回答を見る
Satluj Jal Vidyut Nigam (SJVN)

回答無し