abusesaffiliationarrow-downarrow-leftarrow-rightarrow-upattack-typeblueskyburgerchevron-downchevron-leftchevron-rightchevron-upClock iconclosedeletedevelopment-povertydiscriminationdollardownloademailenvironmentexternal-linkfacebookfilterflaggenderglobeglobegroupshealthC4067174-3DD9-4B9E-AD64-284FDAAE6338@1xinformation-outlineinformationinstagraminvestment-trade-globalisationissueslabourlanguagesShapeCombined Shapeline, chart, up, arrow, graphLinkedInlocationmap-pinminusnewsorganisationotheroverviewpluspreviewArtboard 185profilerefreshIconnewssearchsecurityPathStock downStock steadyStock uptagticktooltiptriangletwitteruniversalitywebwhatsappxIcons / Social / YouTube

์ด ํŽ˜์ด์ง€๋Š” ํ•œ๊ตญ์–ด๋กœ ์ œ๊ณต๋˜์ง€ ์•Š์œผ๋ฉฐ English๋กœ ํ‘œ์‹œ๋ฉ๋‹ˆ๋‹ค.

์ด ๋‚ด์šฉ์€ ๋‹ค์Œ ์–ธ์–ด๋กœ๋„ ์ œ๊ณต๋ฉ๋‹ˆ๋‹ค: English, ็ฎ€ไฝ“ไธญๆ–‡, ็น้ซ”ไธญๆ–‡

๊ธฐ์‚ฌ

2025๋…„ 6์›” 2์ผ

์ €์ž:
Coby Hobbs & Khuon Narim, CamboJA

Cambodia: Thousands of families and environment to be affected by hydropower dam construction on Srekpok 3; forced relocation, lack of assessment and consultation among key issues

ํ˜์˜

"Thousands of Families Face Displacement As Srepok Dam Project Pushes Ahead", 2 June 2025

For thousands of people living along northeast Cambodiaโ€™s Srepok River, upheaval feels inevitableโ€ฆ

After decades on paper, Lower Srepok 3 is finally moving forward, according to a community chief in one of the affected villages, who said officials told him construction will begin later this yearโ€ฆ

While the project site still remains green, almost 4,270 families facing displacement in Ratanakiri and Mondulkiri from the damโ€™s nearly 70,000 hectare planned reservoir are being pushed โ€“ some say even intimidated โ€“ to accept what they call an unjust resettlement dealโ€ฆ

While the designation is not necessarily inaccurate, it blurs the lines of who is ultimately responsible for compensation. Most locals simply pointed to Royal Group as the lead developer, a fact confirmed by provincial authorities.

Further unpacking the ownership structure offers a better picture of the dispersion of the stakeholders. One key entity, identified in a project brief presentation, is China (Cambodia) Rich International Co., which is on the hook for the nearly $83.2 million commitment to the projectโ€ฆ

More directly, the environmental impact assessment (EIA) issued earlier this year names Royal Group Power, the conglomerateโ€™s energy arm, as the official project lead.

According to the EIA, there are two Chinese โ€œtechnical partnersโ€: Huaneng Hydrolancang International Energy Co. and PowerChina Huadong Engineering Co. Together, this team has nudged the long-gestated dam closer to realityโ€ฆ

Meanwhile, as LSP3 nears its first shovel turn, another dam proposal upstream on the Sesan โ€“ the so-called Lower Sesan 3 โ€“ has also lagged behind but is seemingly in feasibility studies.

If both go ahead, as many as 10,000 families across Mondulkiri and Ratanakiri could be affected, said Leang Bunleap, director of the 3S Rivers Protection Network, which assists communities impacted by water diversion projects along the Mekongโ€™s three major tributariesโ€ฆ

A obtained document that summarizes findings from the LSP3 social impact assessment (SIA) conducted in January 2024 puts the total number of families facing displacement once the dam is complete at 4,266, a figure Bunleap confirmedโ€ฆ

Royal Group and its subsidiary, China (Cambodia) Rich International Co., did not respond to repeated requests for comment. Nor did Chinese state-owned partners Huaneng Hydrolancang and Powerchina Huadong Engineering. It is unclear whether more capital injections or investments from the Chinese technical partners are in the pipelineโ€ฆ

Royal Group assistant director Khinn Remy, whose signature appeared on the sign-in sheet, briefly said, โ€œIโ€™m not involved,โ€ before hanging upโ€ฆ