abusesaffiliationarrow-downarrow-leftarrow-rightarrow-upattack-typeblueskyburgerchevron-downchevron-leftchevron-rightchevron-upClock iconclosedeletedevelopment-povertydiscriminationdollardownloademailenvironmentexternal-linkfacebookfilterflaggenderglobeglobegroupshealthC4067174-3DD9-4B9E-AD64-284FDAAE6338@1xinformation-outlineinformationinstagraminvestment-trade-globalisationissueslabourlanguagesShapeCombined Shapeline, chart, up, arrow, graphLinkedInlocationmap-pinminusnewsorganisationotheroverviewpluspreviewArtboard 185profilerefreshIconnewssearchsecurityPathStock downStock steadyStock uptagticktooltiptriangletwitteruniversalitywebwhatsappxIcons / Social / YouTube

هذه الصفحة غير متوفرة باللغة العربية وهي معروضة باللغة English

الدعوى القضائية

Imperial County and Controlled Thermal Resources lawsuit (re lithium mine, USA)

الحالة: ONGOING

Date lawsuit was filed
1 مارس 2024
دقة التاريخ
السنة صحيحة
لا ينطبق
مدافع عن حقوق الإنسان, NGO
موقع رفع الدعوى: الولايات المتحدة الأمريكية
موقع الحادثة: الولايات المتحدة الأمريكية
نوع التقاضي: داخل البلد

الشركات

Controlled Thermal Resources الولايات المتحدة الأمريكية الموارد الطبيعية: عامة, المناجم

Against other:

Government

المصادر

Snapshot: In 2024, advocacy groups Comite Civico del Valle and Earthworks filed a lawsuit to stop Controlled Thermal Resources (CTR), an Australian company, from extracting lithium from the Salton Sea in California, USA. In the lawsuit against the County of Imperial and the company, the plaintiffs allege that the environmental review approved by the County for the Hell’s Kitchen Lithium and Power project, which began construction in January 2024, violates the California Environmental Quality Act (CEQA). The lawsuit claims that the County's environmental review inadequately addresses water usage, potential waste generation, and failed to consult with local Indigenous tribes about mitigation measures.

On 9 January 2025, an Imperial County Superior Court Judge, in a tentative decision, ruled in favour of Controlled Thermal Resources, affirming that the company had met the necessary environmental requirements under CEQA. This decision allows the Hell’s Kitchen project to proceed.

In March 2025, Comite Civico del Valle and Earthworks appealed the dismissal. In their opening brief filed before the Fourth District Court of Appeal in September 2025, they argue that the environmental impact report for the Hell’s Kitchen lithium project overlooks significant risks related to air quality, water consumption, hazardous substances, and tribal cultural resources.

The company denounced a “frivolous legal appeal” and issued a press release.

On 16 July 2026, California's Fourth District Court of Appeal heard oral arguments in the Comité Cívico del Valle/Earthworks appeal against Imperial County's approval of the Hell's Kitchen lithium project.

The case is ongoing.