abusesaffiliationarrow-downarrow-leftarrow-rightarrow-upattack-typeblueskyburgerchevron-downchevron-leftchevron-rightchevron-upClock iconclosedeletedevelopment-povertydiscriminationdollardownloademailenvironmentexternal-linkfacebookfilterflaggenderglobeglobegroupshealthC4067174-3DD9-4B9E-AD64-284FDAAE6338@1xinformation-outlineinformationinstagraminvestment-trade-globalisationissueslabourlanguagesShapeCombined Shapeline, chart, up, arrow, graphLinkedInlocationmap-pinminusnewsorganisationotheroverviewpluspreviewArtboard 185profilerefreshIconnewssearchsecurityPathStock downStock steadyStock uptagticktooltiptriangletwitteruniversalitywebwhatsappxIcons / Social / YouTube

這頁面沒有繁體中文版本,現以English顯示

法律訴訟

Imperial County and Controlled Thermal Resources lawsuit (re lithium mine, USA)

狀態: ONGOING

提訴日期
2024年3月1日
日期準確度
年份正確
不適用
人權維護人士, NGO
申訴地點: 美國
事發地點: 美國
訴訟類型: Domestic

企業

Controlled Thermal Resources 美國 自然資源:綜合, 採礦

Against other:

Government

Sources

Snapshot: In 2024, advocacy groups Comite Civico del Valle and Earthworks filed a lawsuit to stop Controlled Thermal Resources (CTR), an Australian company, from extracting lithium from the Salton Sea in California, USA. In the lawsuit against the County of Imperial and the company, the plaintiffs allege that the environmental review approved by the County for the Hell’s Kitchen Lithium and Power project, which began construction in January 2024, violates the California Environmental Quality Act (CEQA). The lawsuit claims that the County's environmental review inadequately addresses water usage, potential waste generation, and failed to consult with local Indigenous tribes about mitigation measures.

On 9 January 2025, an Imperial County Superior Court Judge, in a tentative decision, ruled in favour of Controlled Thermal Resources, affirming that the company had met the necessary environmental requirements under CEQA. This decision allows the Hell’s Kitchen project to proceed.

In March 2025, Comite Civico del Valle and Earthworks appealed the dismissal. In their opening brief filed before the Fourth District Court of Appeal in September 2025, they argue that the environmental impact report for the Hell’s Kitchen lithium project overlooks significant risks related to air quality, water consumption, hazardous substances, and tribal cultural resources.

The company denounced a “frivolous legal appeal” and issued a press release.

On 16 July 2026, California's Fourth District Court of Appeal heard oral arguments in the Comité Cívico del Valle/Earthworks appeal against Imperial County's approval of the Hell's Kitchen lithium project.

The case is ongoing.