abusesaffiliationarrow-downarrow-leftarrow-rightarrow-upattack-typeburgerchevron-downchevron-leftchevron-rightchevron-upClock iconclosedeletedevelopment-povertydiscriminationdollardownloademailenvironmentexternal-linkfacebookfiltergenderglobegroupshealthC4067174-3DD9-4B9E-AD64-284FDAAE6338@1xinformation-outlineinformationinstagraminvestment-trade-globalisationissueslabourlanguagesShapeCombined Shapeline, chart, up, arrow, graphLinkedInlocationmap-pinminusnewsorganisationotheroverviewpluspreviewArtboard 185profilerefreshIconnewssearchsecurityPathStock downStock steadyStock uptagticktooltiptwitteruniversalityweb

이 페이지는 한국어로 제공되지 않으며 English로 표시됩니다.

이 내용은 다음 언어로도 제공됩니다: English, 简体中文, 繁體中文

이야기

12 3월 2022

Ecuador: Coca Codo Sinclair Hydroelectric Project

For decades, Ecuador faced severe electricity supply shortages, which became even more difficult after 2007 due to severe droughts. As electricity rationing and shortages  put the country’s energy deficit at the centre of public debate, the government of Rafael Correa (in office 2007–17) developed an ambitious energy transition agenda characterised by the construction of large hydroelectric dams. The Coca Codo Sinclair Hydroelectric Project (CCSHP) was promoted as the centrepiece of this plan.

In October 2009, the state-owned Cocasinclair EP signed an engineering, procurement, and construction (EPC) turnkey contract worth 1.9 billion USD with Sinohydro Corporation—one of the key subsidiaries of the Power Construction Corporation of China (PowerChina). The beginning of construction was conditional on the closure of the financing and the bank’s first disbursement. Almost a year later, in June 2010, the credit agreement was signed when China Eximbank provided a loan of 1.7 billion USD to cover 85% of the total cost  estimated in the EPC contract. Construction started in July 2010 and the dam was inaugurated on 18 November 2016—some 10 months later than the deadline set out in the contract.

Project Impacts

  • Employment and Labour Rights: According to official data from Cocasinclair’s parent company, the Electric Corporation of Ecuador (CELEC), during the construction phase, CCSHP generated 6,000 direct jobs and 15,000 indirect jobs. Social conflicts emerged related to noncompliance with labour rights regulations on health and safety and wage issues, as well as issues of discrimination and mistreatment. The breaking point came in December 2014 when the collapse of a pressure well claimed 13 lives.
  • Environment: Since the plant became operational, irreversible environmental effects have been observed in the river basin, including changes in ecological water flows, the disappearance of the San Rafael Waterfall, and regressive erosion processes that are now threatening the sustainability of the plant. On the other hand, as a run-of-the-river project, the CCSHP does not include a massive reservoir and thus is not comparable in terms of carbon emissions with typical mega-hydropower projects, where large reservoirs cause deforestation and decomposing matter releases methane. In fact, there is evidence the dam has led to Ecuador decreasing thermoelectric production and electricity imports from neighbouring countries, resulting in a considerable reduction in carbon dioxide emissions. However, scientists warn that hydroelectric plants such as CCSHP are vulnerable to climate change.
  • Local Community: No displacement of people or violations of indigenous rights have been reported in relation to this project—unlike many other mega-dam projects in the region. However, local communities have suffered loss of livelihoods, declines in agricultural production for local consumption, and livestock and fishing activities. Although the construction of the project generated employment and boosted the local economy, since the plant became operational, there has been a slowdown in the local economy and an increase in unemployment. Local inhabitants have been unable to resume the traditional work that ensured their subsistence.
  • Governance: Social participation in CCSHP has been deficient in terms of both quantity and quality. There is a lack of transparency and access to information. The project has also been tainted by cases of corruption, bribery, and cost overruns.

People's Map of Global China

타임라인

개인정보

이 웹사이트는 쿠키 및 기타 웹 저장 기술을 사용합니다. 아래에서 개인정보보호 옵션을 설정할 수 있습니다. 변경 사항은 즉시 적용됩니다.

웹 저장소 사용에 대한 자세한 내용은 다음을 참조하세요 데이터 사용 및 쿠키 정책

Strictly necessary storage

ON
OFF

Necessary storage enables core site functionality. This site cannot function without it, so it can only be disabled by changing settings in your browser.

분석 쿠키

ON
OFF

귀하가 우리 웹사이트를 방문하면 Google Analytics를 사용하여 귀하의 방문 정보를 수집합니다. 이 쿠키를 수락하면 저희가 귀하의 방문에 대한 자세한 내용을 이해하고, 정보 표시 방법을 개선할 수 있습니다. 모든 분석 정보는 익명이 보장되며 귀하를 식별하는데 사용하지 않습니다. Google은 모든 브라우저에 대해 Google Analytics 선택 해제 추가 기능을 제공합니다.

프로모션 쿠키

ON
OFF

우리는 소셜미디어와 검색 엔진을 포함한 제3자 플랫폼을 통해 기업과 인권에 대한 뉴스와 업데이트를 제공합니다. 이 쿠키는 이러한 프로모션의 성과를 이해하는데 도움이 됩니다.

이 사이트에 대한 개인정보 공개 범위 선택

이 사이트는 필요한 핵심 기능 이상으로 귀하의 경험을 향상시키기 위해 쿠키 및 기타 웹 저장 기술을 사용합니다.